CURRENT PROJECTS
Ōhaupō Village Signalised Pedestrian Crossing - Project commenced 24/10/2023
Works on stage 2
- We will start with removing the footpaths and kerbing highlighted in orange on the below image.
- We will have the east side of the road from the Ōhaupō Drinks Station to the pines past the dairy blocked off for parking as well as from the west side of the road from The Bakehouse south the Great Collins.
- We are aiming to have this completed mid-March weather pending and will endeavour to complete sections of this as we can where construction allows.
- Stage 3 will follow completing speed calming measures including thresholds, speed reducing tables and the signalised crossing.
Please respect our lower speed limits in order to keep our team & you safe.
We thank you in advance for your cooperation and patience throughout the construction phase of this fantastic Ōhaupō Village improvement.
Read more about this project here.
Rifle Range Road - Project commenced 12/07/2024
As a team, we are very proud of the work we have accomplished on this project. These road upgrades provide safe, independent routes to and from school for children in the four schools in the area. While Swarbrick Park's parking will look different, the majority of car parking has been retained.
We are working quickly and have completed the following - right on time!
400m of separated bike lane on Rifle Range Road
Raised safety platforms on Aberdeen Drive and Rifle Range Road
Improved the Johnson Street footpath, kerb and berm