Latest Projects.
Latest Projects.
Kay Road Subdivision Stage 2 & 3
Client: Hamilton Residential Limited
Location: Kay Road, Hamilton
Original Contract Period: 10 Months
Actual Construction period: 10 Months
Works completed under this contract include:
- Earthworks over 40,000 m3 (In progress)
- Environment Controls
- Retaining Wall
- Stormwater Drainage
- Wastewater Drainage
- Subsoil Drainage
- Kerb Construction
- Service Installation
- Water Reticulation
- ROW and Footpath Construction
- Pavement Construction
- Surfacing
- Signs and Roadmarking
Kay Road Subdivision Stage 2 & 3
Client: Hamilton Residential Limited
Location: Kay Road, Hamilton
Original Contract Period: 10 Months
Actual Construction period: 10 Months
Works completed under this contract include:
- Earthworks over 40,000 m3 (In progress)
- Environment Controls
- Retaining Wall
- Stormwater Drainage
- Wastewater Drainage
- Subsoil Drainage
- Kerb Construction
- Service Installation
- Water Reticulation
- ROW and Footpath Construction
- Pavement Construction
- Surfacing
- Signs and Roadmarking
Progressing on from Stage 1 – 55 Lot Development, we have started Stage 2 & 3 – 90 Lot Development and are well into the earthworks.
Good planning and placement of the sediment retention pond in Stage 1 has allowed us to keep on using this as our sediment pond for Stage 2 & 3 with minor adjustments to accommodate the larger work area exposed. To date we have stripped 10500 m3 of topsoil, imported around 22,500 m3 as well as around 5,000 m3 of cut to fill onsite. There is still another 9,000 m3 scheduled to be imported. We have had difficulties with the weather being the negating factor, which resulted in few good days of potentially shifting material in and around site been lost to allow the site time to dry out.
As the earthworks reaches completion we will start getting stuck into installing all the stormwater and wastewater drainage. This has been scheduled at 32 manholes and over 3000m of pipe to be laid, which alongside the retaining wall construction, pond construction and shaping of the carriageway subgrade will fill in our current summer season. We have July/August set as our target completion with the mind set of trying complete the work sooner to give the developer an earlier window of opportunity to start constructing the smart 90 medium density housing development.
The developer has indicated many houses have already sold off the plans so if you are interested in a property for living or investment they look very good.
Contact details are:
Lincoln Archer
Yeoman Property Group
Lincoln@yeoman.co.nz
Follow Yeoman Property Group on Facebook
07 834 0015 or 021 637 455
Te Rahu Toad Stage 2
Client: Kauri Ridge Developments
Location: Te Rahu Road, Te Awamutu
Original Contract Period: 12 Weeks
Actual Construction period: 12 Weeks
Works to be completed under this contract include:
- Earthworks – 1500m3
- Stormwater Drainage 550m
- Wastewater Drainage 500m
- Subsoil Drainage – 460m
- Kerb Construction – 460m
- Service Installation – 460m
- Water Reticulation – 630m
- ROW and Footpath Construction – 1100m2
- Pavement Construction – 2200m2
- Surfacing – 2200m2
- Hydroseeding
- Signs and Roadmarking
Te Rahu Toad Stage 2
Client: Kauri Ridge Developments
Location: Te Rahu Road, Te Awamutu
Original Contract Period: 12 Weeks
Actual Construction period: 12 Weeks
Works to be completed under this contract include:
- Earthworks – 1500m3
- Stormwater Drainage 550m
- Wastewater Drainage 500m
- Subsoil Drainage – 460m
- Kerb Construction – 460m
- Service Installation – 460m
- Water Reticulation – 630m
- ROW and Footpath Construction – 1100m2
- Pavement Construction – 2200m2
- Surfacing – 2200m2
- Hydroseeding
- Signs and Roadmarking
Stage 2 consists of 17 Lots around 650m2 in Te Awamutu. The subdivision consists of the main carriageway, Te Aranui Drive, spanning 150m long and 11m wide. It is Councils plan to link Te Rahu Road and Cambridge Road sometime in the future via Te Aranui Drive hence the 11m width requirement.
There is also a short 40m length of carriageway off Te Aranui Drive at the start of Stage 2 construction as well as three Right of Ways off Te Aranui Drive each servicing two sections.
Webster Road Subdivision
Client: Beckside Developments
Location: Webster Road, Matangi
Original Contract Period: 12 Weeks
Actual Construction period: 10 Weeks
Works completed under this contract include:
- Earthworks 4,900m3
- Subsoil Drainage 950m
- Stormwater Drainage 80m
- Water Reticulation 450m
- Pavement 2,500m2
- Surfacing 3,400m2
Base Civil has recently completed a rural subdivision in Matangi on behalf of Blue Wallace Surveyors.
The roadway was formed with over 4,000m3 of cut to fill taking place. A swale drain was formed either side of the road which included 24 catchpit soakholes and 950m of subsoil drainage. This made way for a solid 500mm deep pavement.
Webster Road Subdivision
Client: Beckside Developments
Location: Webster Road, Matangi
Original Contract Period: 12 Weeks
Actual Construction period: 10 Weeks
Works completed under this contract include:
- Earthworks 4,900m3
- Subsoil Drainage 950m
- Stormwater Drainage 80m
- Water Reticulation 450m
- Pavement 2,500m2
- Surfacing 3,400m2
Base Civil has recently completed a rural subdivision in Matangi on behalf of Blue Wallace Surveyors.
The roadway was formed with over 4,000m3 of cut to fill taking place. A swale drain was formed either side of the road which included 24 catchpit soakholes and 950m of subsoil drainage. This made way for a solid 500mm deep pavement.
Water, power and telecommunications were provided to each of the 8 generously sized lots. Each section was completed with a sealed entranceway.
We worked hard along with the decent weather in order to get the project finished with time to spare. The immaculate finish will no doubt make these attractive buys. Get in quick, these sections won’t last long.
Pukete Road Cycleway
Client: Hamilton City Council
Location: Pukete Road, Hamilton
Original Contract Period: 4 Weeks
Actual Construction period: 4 Weeks
Works completed under this contract include:
- Earthworks 500 m3
- Fencing
- Asphalt Cycleway 2150 m2
- Sewer/Water Drainage
- Roadmarking
- Signs/Sight Rails
Hamilton City Council contracted Base Civil Limited to complete the joining section for the Te Awa Great NZ River Ride Cycleway along Pukete Road after failing to secure linking land along the riverside.
Having completed the temporary metal track a number of years ago, we were very familiar with the site.
Pukete Road Cycleway
Client: Hamilton City Council
Location: Pukete Road, Hamilton
Original Contract Period: 4 Weeks
Actual Construction period: 4 Weeks
Works completed under this contract include:
- Earthworks 500 m3
- Fencing
- Asphalt Cycleway 2150 m2
- Sewer/Water Drainage
- Roadmarking
- Signs/Sight Rails
Hamilton City Council contracted Base Civil Limited to complete the joining section for the Te Awa Great NZ River Ride Cycleway along Pukete Road after failing to secure linking land along the riverside.
Having completed the temporary metal track a number of years ago, we were very familiar with the site.
The site was filled, drainage improvements carried out along with approx 700lm of new cycleway in asphalt an timber edging. We also installed a sight rail painted white along the length to separate the cyclist from the traffic along with a push button warning sign for the road crossing to warn motorist when cyclists are crossing.
With limited time for completion prior to the end of financial year we were able to battle the winter elements completing the project with only days to spare and a very happy client.