Our Completed Projects

Hamilton Park City Road & Drainage Extension

Client: Hamilton City Council
Location:
Newstead Cemetery, Hamilton
Original Contract Period:
12 Weeks
Actual Construction period:
11 weeks used including additional works - June 2013

Work completed under this contract included:

  • Earthworks
  • Drainage
  • Water Reticulation
  • Kerb and Channel
  • Pavement Construction
  • Surfacing – Chipseal
 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
The HCC Cemetery upgrade included excavation for new roadways, drainage installations for this and future extensions of the cemetery, water reticulation upgrades and approx. 400m of full new road construction. Drainage extended over 500m with new manholes lines up to 450mm diameter out to a new gully outlet.

The roading upgrade had to be completed in a sensitive environment as adjacent areas were still holding services throughout the works. Our crews shutdown and had smoko breaks to ensure cemetery users were not inconvenienced by noise or activities during those times.

The work was completed well within the contract timeframes with very satisfied council and cemetery staff.

Find out more about our Roading Services

Rora Street Pavement Rehabilitation

Client:
Waitomo District Council
Location:
Rora Street, Te Kuiti
Original Contract Period:
12 Weeks
Actual Construction period:
Completion - May 2011


Work completed under this contract included:

  • Earthworks
  • Drainage
  • Pavement Construction
  • Surfacing - Chipseal & Asphalt

This contract involved the removal of the 3 areas main street pavement in Te Kuiti, replacing and resurfacing. There were also some entranceways involved.

Extensive consultation was carried out including a meeting with business owners to explain the works, various traffic management options and recommendations. This was agreed with shop owners and work commenced. Unfortunately unsuitable material was encountered so the pavement had to be re-designed, fully undercut, geotextile installed.
 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
Base Civil assisted in the re-design and also re-designed the pavement levels to better fit in with the surrounding kerbs and carparks with no additional charges. One section was delayed for two weeks to make way for the running of the sheep, and yet the project was still completed within the tender timeframe with very good results.

Find out more about our Roading Services

Rora Street Sewer Installation

Client:
Waitomo District Council
Location:
Rora St Sewer Installation                       
Original Contract Period:
5 Weeks
Actual Construction period:
4 Weeks, Completion – April 2011

Work completed under this contract included:

  • Excavation
  • Live Sewer and Manhole Installation
  • Pavement reinstatement – Chipseal/SMA

This Contract involved the installation of 300mm and 150mm sewer line at 2.5m deep in the main street of Te Kuiti.

This work needed to be carried out live and at night due to the location of the works. This was successfully completed in the required timeframes even with adjustments, design changes and additional works. This included 9 live connections 32m 300mm SN16, 150m 150mm SN16, 3 manholes and associated reinstatement.

Find out more about our Drainage Services

 
  • image 01
  • image 01
  • image 01
  • image 01

Te Anga & Taharoa Road Pavement Rehabs

Client:
Waitomo District Council
Location:
Te Anga & Taharoa Roads, Waitomo
Original Contract Period:
12 Weeks
Actual Construction period:
10 weeks, including 1 week delay from aggregate supplier – November 2010

Work completed under this contract included:

  • Earthworks
  • Drainage
  • Pavement Construction
  • Surfacing - Chipseal

This contract involved two separate roading rehabilitations.

Taharoa Road was a low lying area prone to extensive flooding over the road during winter periods and Te Anga Road was a climbing hill sections heading up out of Waitomo. The contracts involved culvert replacements and clearing before undercutting shoulders, backfilling and overlaying the road. Mass block walls were required in some areas to support shoulders.

Both roads were completed within contract timeframes, despite additional work being added for undercutting significant additional failed areas identified prior to commencing.

Find out more about our Roading Services

 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01

Te Anga Road Pavement Rehabilitation

Client:
Waitomo District Council
Location:
Te Anga Road, Waitomo
Original Contract Period:
12 Weeks
Actual Construction period:
10 weeks used – December 2011

Work completed under this contract included:

  • Earthworks
  • Drainage
  • Pavement Construction
  • Surfacing – Chipseal

This contract involved the rehabilitation of over 1.1km of winding steep road on the approach to Te Anga itself well beyond Waitomo. It is a remote but reasonably busy road with tourist and logging activities.

The contract involved extensive culvert replacements and outlet structures throughout the hill, installation of block retaining walls to retain slip areas, cutting and shifting lanes into the hill to avoid steep slip areas, installation of subsoil drainage and filling watertables to create pavement width, digouts, shoulder work and overlaying the entire section.
 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
During initial digout work it was identified that the top pavement layer from a previous overlay was failing meaning the entire top basecourse layer needed to be removed and replaced. Base Civil Limited came up new smart solutions, completed a full survey and long section design, scheduled new quantities and carried out the work which was not extensively more expensive than the tendered price but a far superior solution with more works. This was all completed short of the contract period and sealed before the Christmas break which was an excellent outcome of all parties and road users.

Find out more about our Roading Services

Long & Roto Streets Upgrade

Client:
Waikato District Council
Location:
Various Waikato District
Original Contract Period:
9 Weeks
Actual Construction period:
9 Weeks, Completion – August 11 (extended-additional work/wet days)

Work completed under this contract included:

  • Earthworks
  • Drainage – Extensive stormwater
  • Pavement Construction
  • Kerbing and Footpaths
  • Entranceway Construction
  • Surfacing – Chipseal

The contract was for two urban upgrades. They both involved stormwater, kerbing, footpaths, entranceways and pavement construction and surfacing.

Roto St

Roto Street in Te Kauwhata was approx. 200m of roadway and an intersection. Drainage was installed with new catchpits before new kerbing and footpaths were installed. The pavement was then constructed and surfaced. The job went well and the residents were very happy with the outcome in terms of both quality and time.
 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
This was a challenging contract which very poor weather made more difficult. The street was very steep and involved over 250m of stormwater lines (300 & 375mm), manholes etc at over 2.0m deep. The road then required kerbing to be installed on both sides, footpaths, large entranceways due to set back boundaries then full pavement and surfacing. There were many old and hidden services which required relocation and property drainage connections which needed to be hooked into the network.  The job was under designed and therefore the tender budget was exceeded by some $80,000 but residents on the street all commented about the quality, the excellent staff and communication and superb outcome.
 
Find out more about our Services

K & C Upgrade Works

Client:
Waikato District Council
Location:
Various Waikato District
Original Contract Period:
10 Weeks
Actual Construction period:
10 Weeks, Completion – 30 June 2010 (extended with additional works)

Work completed under this contract included:

  • Earthworks
  • Drainage - culvert and soak hole installation
  • Pavement Construction
  • Kerbing and Footpaths
  • Entranceway Construction
  • Surfacing - Chipseal

This contract started as two kerb and channel jobs in and near Ngaruawahia.

The original jobs were installation of new drainage including stormwater lines and catchpits, and the installation of kerb and channel to non-kerbed roads for over 1km. Significant extensions were made to the sites being, Waikato Esplanade in Ngaruawahia and Waingaro Road, Glen Massey. The esplanade site was extended approx. 200m, and Glen Massy became both sides of the road and more than doubled in size.

 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
Then sites were added as follows:
 
  • Ngaruawahia Bowling Club – install kerbing, shape prepare and seal carpark and crossings.
  • Waerenga Road, Te Kauwhata – Install new pedestrian crossing including Centre Island, entranceways and footpath.
  • Keith Road, Waerenga – Widening, pavement and surfacing of carparking for Cemetery.
  • Bow Street Raglan – Removal and installation of new raised, paved pedestrian crossings in the main street of Raglan. This involved extensive consultation, notification and closing of the main street. The shop owners were extremely nervous about the contract due to previous time overruns by previous contractors, but everything ran to time and the street was opened early.
Find our more about our Services

2022 River Road, Subdivision

Client:
Fred & Sue Landon
Location:
2022 River Road
Original Contract Period:
6 Weeks
Actual Construction period:
5 Weeks, Changes to intersection by council delayed final completion

Find out more about our Subdivision Services

 
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01

Waipa Networks Yard

Client:
Fosters Construction Limited
Location:
Waipa Networks Yard
Original Contract Period:
 
Actual Construction period:
9 Months, Completion – Nov 10 (Extended for additional Road)

Work completed under this contract included:

  • Earthworks
  • Drainage – Pipes, Manholes, Catchpits
  • Sewer – Pipes, Manholes
  • Kerbing/Concrete Works
  • Pavement Construction
  • Surfacing

This contract involved all siteworks for the construction of a new premise in Te Awamutu.

Including were significant excavation and sand fill for foundations, approx 800m of stormwater drainage from 450mm to 150mm including manholes and connections, approx 200m of Sewer from 150mm to 100mm including significant plumbing to edge of building, and all carpark construction for asphalt and concrete.

 
  • image 01
  • image 01
  • image 01
  • image 01
 